10 Hill Head Coastal Protection Project Phase 1 Scheme PDF 123 KB
A report by the Director of Planning and Regulation.
Additional documents:
Decision:
RESOLVED that the Executive:
(a) approves the beach re-nourishment to replenish the historically low beach levels at Hill Head and implement extensive maintenance repairs to FBC owned groynes at Hill Head;
(b) approves proceeding with Detailed Design of the replacement seawall along frontage ‘A’ including Ground Investigation works; and
(c) in the interest of expediency, approves that the Director of Planning and Regulation is given delegated authority to award the contracts to deliver Phase 1 of the Hill Head Coastal Protection Project, after consultation with the Executive Member for Planning and Development.
Minutes:
At the invitation of the Executive Leader, Councillor C J Wood addressed the Executive on this item.
The Executive was advised that officers are planning a public information event to be held on 11 August on the phase 1 works to include an exhibition of posters and timescales giving examples of possible disruptions i.e. access restrictions to car parks at the site.
RESOLVED that the Executive:
(a) approves the beach re-nourishment to replenish the historically low beach levels at Hill Head and implement extensive maintenance repairs to FBC owned groynes at Hill Head;
(b) approves proceeding with Detailed Design of the replacement seawall along frontage ‘A’ including Ground Investigation works; and
(c) in the interest of expediency, approves that the Director of Planning and Regulation is given delegated authority to award the contracts to deliver Phase 1 of the Hill Head Coastal Protection Project, after consultation with the Executive Member for Planning and Development.