RESOLVED that the Executive agrees that:
(a) the remaining capital budget for 2017/18 is allocated to undertake the repairs;
(b) the balance of funding required is brought forward from 2018/19 revenue budget; and
(c) the decision to appoint the successful contractor be delegated to the Director of Finance and Resources and the Executive Member for Leisure and Community.