To approve the inclusion of the site-specific Fort Fareham appendix (Appendix A to the report) with the Fareham Housing Regeneration Strategy.
To note the contents of Appendix A to the report which details the energy efficiency works being undertaken to the Council owned properties at Fort Fareham estate.
To note that a budget has been set aside for the energy efficiency works to be undertaken, however, other aspirational works will require further investigation.
To also agree in principle the redevelopment of Redoubt Court and the additional works to further improve the site, should budgets allow.
The Regeneration Strategy was adopted at the 01 March 2021 Executive meeting. The Strategy details the factors that will be considered when identifying and progressing housing regeneration opportunities. Appendix A is the second of the individual site-specific appendices produced for Executive approval.
The age and type of build of the homes at Fort Fareham estate mean that the energy efficiency is typically poor. Appendix A details the improvement works that will help reduce energy costs for the Council’s tenants and improve the condition of the properties. The project is separated into several areas: houses, flats, Redoubt Court and other improvements.
Redoubt Court has been identified in the emerging Local Plan as having potential for further affordable housing.
It is worth noting that there is little scope to redevelop Fort Fareham as a whole due to the high level of private ownership. Some private owners have already made improvements to their homes to address the inherent thermal issues.
The ‘aspirational’ area of the project outlines how to further improve the immediate area. These additions may only go ahead if budgets allow. They include enhanced greener installations, removal of the drying areas to provide private gardens for tenants and a community orchard with wildflower grassland. Further details of this and the other projects are outlined in the report.
Decision type: Key
Decision status: Recommendations Approved
Notice of proposed decision first published: 07/10/2022
Decision due: 7 Nov 2022 by Executive
Lead member: Executive Member for Housing
Lead director: Deputy Chief Executive Officer
Contact: Fleur Allaway Email: fallaway@fareham.gov.uk.
Consultees
None
Background Papers: None