To agree funding for a five-year programme of essential repairs and maintenance for the Streetscene public buildings and infrastructure.
To continue to provide and maintain a good and safe standard of public toilets. sports pavilions and public spaces infrastructure, Property Services have undertaken a condition survey to identify essential repairs and maintenance required over the five years 2023 to 2028.
The information from the condition survey has been formulated into an Asset Management Plan for the Streetscene property portfolio that identifies the phased capital investment required over the next five years.
The report provides a summary of the essential repairs and maintenance required and an estimated budget figure for the cost of the works.
RESOLVED that the Executive:
(a) agrees the delivery of a five-year Asset Management Plan for the Streetscene public buildings and infrastructure as set out in the Executive Briefing Paper; and
(b) approves the funding required to complete the works in the Streetscene Asset Management Plan, as detailed in paragraph 25 of the Executive Briefing Paper.
Report author: Mark Bowler
Publication date: 08/03/2023
Date of decision: 06/03/2023
Decided at meeting: 06/03/2023 - Executive
Effective from: 18/03/2023
Accompanying Documents: