skip navigation
MyAccount
Mobile Site
Full Site
Accessibility
Contact Us
A B C D E F G H I J K L M N O P Q R S T U V W X Y Z


Home
Pay for it Apply for it Report it Latest News What's On

You are here: Home / About The Council / Decision details

Quick Links

 Meetings, agendas and minutes

 Calendar

 Committees

 Constitution

 Election Results

 Decisions

 ePetitions

 Notice of Key Decisions

 Library

 Meetings

 Outside bodies

 Search documents

 Subscribe to updates

 What's new

 Your Councillors

 Your County Councillors

 Your MEPs

 Your MPs

Decision details

Daedalus Investment Project - Progress Update

Decision Maker: Executive

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Purpose:

The purpose of this report is to update Members on progress with the Daedalus Investment project.

 

In July 2013, the Executive supported a proposal to develop an Innovation Centre for new start up businesses at the Solent Enterprise Zone, undertake improvements to the airfield and develop new hangar space. In October 2013, the Executive agreed revised funding arrangements for the project and in November 2013 agreed a governance and decision-making structure and the establishment of a Member Working Group to oversee the project.

 

The project contained some very challenging timescales, principally the requirement to complete the Innovation Centre by the end of March 2015. This aspect of the project is progressing extremely well.  Planning consent was granted on 26 March 2014 and site preparation works commenced on 12 May.  Construction work on the site commenced on 2 June and the completion date is programmed for early March 2015. A procurement process is currently under way with a view to appointing an operator for the centre during the summer of 2014.

 

The work to improve the runway is still planned to commence during September 2014 and be complete by the end of November 2014.  This will minimise disruption to planned airfield activities during the summer months. The specification for the works is intended to enable the airfield operator to obtain a CAA licence which will enhance its commercial potential.

 

Work has been ongoing with the Homes and Communities Agency (HCA) to identify a suitable location on the airfield for the development of new hangar space.  This is dependent on agreement of an overall strategy for the airfield between the HCA, FBC and other interested parties including Hampshire County Council (HCC), the Solent Local Enterprise Partnership (SLEP) and the airfield operator.  As a result it is now likely that new hangar space will be delivered during the latter half of 2015.

Decision:

RESOLVED that the Executive notes the progress made to date on the Daedalus Investment Project.

 

Report author: Colin Mitchell

Publication date: 07/07/2014

Date of decision: 07/07/2014

Decided at meeting: 07/07/2014 - Executive

Effective from: 18/07/2014

Accompanying Documents:

 

 




Browse

Follow us

Facebook Twitter You Tube Flickr

View Fareham
Today online





Fareham Borough Council, Civic Offices, Civic Way, Hampshire, PO16 7AZ
Tel: +44 (0) 1329 236100 | Mobile Text/Photo: 07860 098627 | Fax: +44 (0) 1329 821770
Read page with Browse Aloud GOV.UK Get Safe Online
Fareham Borough Council: List of RSS Feeds