Decision Maker: Executive
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
To advise the Executive on the updated costs for the preparation of the Welborne Plan.
This report sets out the latest projected and incurred expenditure relating to the development of the Welborne Plan.
The Council has received significant Large Sites Capacity Funding from the Department of Communities and Local Government (DCLG) to assist with the planning and delivery of Welborne. The Council is in continued dialogue with DCLG in relation to opportunities for further capacity funding for 2014/15.
RESOLVED That the Executive notes the update on the financial costs of producing the Welborne Plan.
Report author: Claire Burnett
Publication date: 08/10/2014
Date of decision: 06/10/2014
Decided at meeting: 06/10/2014 - Executive
Effective from: 18/10/2014
Accompanying Documents: