Decision Maker: Executive
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
To advise the Executive of the outturn cost for the Council car park and pedestrian highway works and to detail the key reasons behind the overspend on this project.
In September 2013 the Executive approved the award of contract for the resurfacing and repairs of numerous car parks and footways around the borough. The contract was awarded to Colas Limited in the sum of £329,460.93.
The final account for the project has been agreed at £511,268 which is 55% over the approved contract sum.
This report details the main reasons for the overspend and advises the Executive that this has been funded from within existing budgets.
RESOLVED that the Executive notes the report.
Report author: Ian Cousins
Publication date: 19/05/2016
Date of decision: 16/05/2016
Decided at meeting: 16/05/2016 - Executive
Effective from: 02/06/2016